Cooling Designer
English
Request a demo

Cooling Designer

Desktop software that sizes the liquid cooling of an AI data hall and issues the design package.

You enter the site and the rack list. You get the sized plant, a full-year energy model, the rule checks, the report, the drawings and the BIM model.

  • 16 design steps in one model
  • 8,760 hours of the site's weather
  • Windows and macOS, works offline

See it work

Hall A, Frankfurt, from a new project to the issued report: the 3D build of the hall, then all 16 steps. 70 seconds.

What you put in, what you get out

One project goes from an empty site to an issued revision. You do not need a spreadsheet or a second tool.

You put in

  1. The site: a point on the map or its coordinates.
  2. The rack list: from the rack library, or a CSV file with the columns rack and kw.
  3. The build phases: the date of each phase and the racks in use.
  4. The cooling architecture: direct-to-chip, rear-door, immersion or air.
  5. The equipment: from the library, or your vendor's datasheet with its pump curve.
  6. Your project limits: pipe velocity, pressure drop per metre, design margin, noise limit at the boundary, slab rating.

You get out

  1. The sized plant: CDUs, pumps, pipe sizes, dry coolers, chillers, fan walls, heat exchangers and the heat pump.
  2. The year: annual and monthly PUE, WUE, water by source, energy, running cost and carbon.
  3. The checks: each rule of the site with pass, warning or fail, and the source of the rule.
  4. The files: report, equipment schedule, calculation log, 6 drawing sheets, IFC model, BMS points list, CFD layout, commissioning test sheets and a 3D video.

Hall A, Frankfurt, the sample project

IT load
10.86 MW
Racks
100
To liquid
9.50 MW
CDUs
7 + 1 × 1.5 MW
Annual PUE
1.12
Checks
16 pass · 0 fail

The engineering process, in 16 steps

A project goes through three phases. The app keeps the steps in this order, and each step uses the results of the steps before it.

0133.1 °C

Site and climate

Pick the place. The app loads a typical weather year and 25 years of hourly data for the design conditions.

Design dry bulb, wet bulb, freeze case
0210.86 MW

IT load

Rack groups from the rack library or a CSV list, with build phases. The heat splits into liquid and air.

100 racks, 9.50 MW to liquid
03DLC

Architecture

Direct-to-chip, immersion, rear-door or air. The schematic follows the choice.

Direct-to-chip with in-row CDUs
0435 / 45 °C

Liquid loop

The rack loop and facility water, with CoolProp fluid data at the loop's mean temperature.

7 + 1 CDUs, flow, pumps, hoses
05PUE 1.12

Heat rejection and energy

Dry coolers, adiabatic hours and trim chillers, run for all 8,760 hours of the year.

Annual PUE, WUE, energy, water
06ERF 16.9%

Heat reuse and carbon

A heat pump to district heating, the reuse factor, CUE and the carbon of the year.

3.86 MW to the heat network
07N+1

Redundancy

Each failure case: one or two CDUs, a pump, two dry coolers, a heat exchanger, a chiller, and a power loss with its ride-through.

Plant power and the cases per phase
08Leaks

Leaks, fluid and controls

Leak zones with their sensors and the action of each, the fluid volume and the fluid quality limits.

Leak plan, setpoints, BMS points list
093D

Floor plan and 3D model

The hall drawn from the design: rows, CDUs, pipes and the yard, with a build tour in 3D and a video.

Plan, 3D view, presentation video
103 options

Compare options

Copies of the design side by side, each run for the full year: energy, water, heat reuse and cost.

The best value in each row marked
1124 checks

Checks

Every rule for the site, global, EU and national, run again after each change.

16 pass, 5 warnings, 0 fail
1211 pages

Report

The design report: the summary, the basis, the loop, the plant, the checks and the appendices.

PDF, XLSX schedule, CSV log
136 sheets

Drawings and model

Schematic, hall layout, piping and the plant yard, on your CAD layer standard, and the BIM model.

PDF, DXF, IFC 4.3
14L1 to L5

Commissioning

The test plan from the factory tests to the integrated full-load test with load banks. Each level has its signer and each test its pass value.

Test sheets for each level
15Rev A

Revisions and review

Review, approve and issue. An issued revision is signed and locked, and new work goes into a new draft.

Signed, locked revisions
16Linked

Files and photos

Datasheets, site photos and vendor files, kept with the project and linked to the values they prove.

Files beside their values

These actions need a person's approval

  • Issue a revision
  • Make an option the design
  • Change a rule
  • Apply a change from the AI assistant
  • Delete a project or a file

What it calculates, step by step

Each step takes the results of the step before it. When you change one input, every later step calculates again.

  1. 01

    Site and climate

    33.1 °C design dry bulb

    Calculates
    The design dry bulb, the design wet bulb and the freeze case from 25 years of NASA POWER hourly data. The PVGIS typical year for the annual model. The free-cooling hours at your dry cooler supply temperature.
    You get
    Design values with their source, an editable margin for grid data, and the free-cooling hours for each degree of supply temperature. You can import your own EPW file.
  2. 02

    IT load

    10.86 MW · 9.50 MW to liquid

    Calculates
    The IT load of each rack group (rack type, count, power, liquid share) and the split of the heat into liquid and air, for each build phase.
    You get
    The load per phase. The rack library holds 14 AI platforms, from DGX H100 to Vera Rubin NVL144 CPX and Rubin Ultra NVL576, each value with its source and date.
  3. 04

    Liquid loop

    7 + 1 CDUs of 1.5 MW

    Calculates
    For the rack loop and the facility water: the flow, the pipe size of each run, the velocity, the pressure drop per metre, the pressure drop on the worst path and the pump duty. The load on each CDU in normal operation and with one CDU out. Fluid data from CoolProp 8.0.0 at the mean temperature of the loop.
    You get
    The pipe schedule, the pump duty and the CDU count. Other loop types: rear-door heat exchangers, single-phase immersion, two-phase direct-to-chip and liquid-to-air CDUs.
  4. 05

    Heat rejection and the full year

    PUE 1.12 · WUE 0.066 L/kWh

    Calculates
    The dry coolers, the adiabatic spray hours, the trim chillers for hot and humid hours and the fan walls, hour by hour for 8,760 hours. The glycol share from the 20-year minimum temperature. The noise at the site boundary at night.
    You get
    PUE for each month and for the year, WUE, water by source (town water, rain water, treated grey water), energy, running cost in your currency, the freeze point, the night noise and a forecast of the EU A to G rating.
  5. 06

    Heat reuse and carbon

    ERF 16.9% · 3,857 kW to the network

    Calculates
    A heat pump to a district heating network: its supply temperature, COP, hours and delivered heat. The energy reuse factor (ERF), the carbon usage effectiveness (CUE) and the carbon of the year, with the grid carbon intensity from Ember.
    You get
    The ERF against the site's target for each year, the shortfall in MWh when there is one, and the ways to reach the target.
  6. 07

    Redundancy and power

    N+1 met

    Calculates
    Each failure case: one CDU out, two CDUs out, a facility water pump out, two dry coolers out, a heat exchanger out, a glycol pump out, a chiller out, and a grid loss. For each case, the capacity left against the load. The power list of the cooling plant and the UPS fit. The part load of CDUs and chillers in each build phase.
    You get
    A pass or fail for each case, the plant power list, and a warning when a unit runs below its lowest stable load. You can try N+2 on a copy of the design.
  7. 08

    Leaks, fluid and controls

    BACnet/IP or Modbus TCP

    Calculates
    The leak zones with their sensors and the action of each zone. The fluid volume and the fill. The margin between the rack loop supply and the dew point of the hall. The ride-through after a power loss: the seconds until the racks reach their limit, against the fan restart time.
    You get
    The leak plan, the fluid volume, the setpoints, the failure scenarios and the BMS points list as CSV or XLSX for the controls contractor.
  8. 09

    Floor plan and structure

    kN/m² against the slab

    Calculates
    The positions of the racks and units in the hall, the air temperature at the rack inlet (2D estimate), and the floor load with a CDU full of fluid, against the slab rating.
    You get
    The hall layout and a CSV of rack positions, loads and unit data for a CFD tool.
GPU racks in rows with their cold-plate manifolds, cyan supply and amber return

Try it: change the rack loop ΔT

10 Ksupply 35 °C, return 45 °C
Total flow
14,228 L/min
Rack-loop pumps
55.8 kW
Return to the CDUs
45 °C

Hall A, 9.50 MW to liquid, PG25, 50 mm rack hoses. Values from the liquid loop step of the app.

The draft hall in 3D

The app draws the hall in 3D from the design while it is still a draft. When you change the racks, the CDUs, the pipes or the yard, the 3D model changes at once. The hall at the top of this page uses the same geometry.

The 3D view of Hall A in the app: the hall with four rows of GPU racks, the fan walls, the CDUs, the pumps and tank, and the yard of 13 + 2 adiabatic dry coolers

Every rule, checked after each change

The location of the site selects the rule sets: global, then the EU, then the country. Each check shows the value, the limit, the status and the source of the rule. A rule that the app cannot check shows as a note, never as a pass.

Hall A: 16 pass, 5 warnings, 3 notes, 0 fail

Project limits16

  • Rack coolant inletRack loop supply against the rack vendor's limit
    Warning
  • Pipe velocityFastest pipe against your limit in m/s
    Pass
  • Pressure dropWorst run in Pa/m against your limit, with the pipe size that passes
    Warning
  • CDU redundancySpare CDUs against your N+ target
    Pass
  • Dry cooler marginMargin with the standby units out, pump heat included
    Pass
  • Freeze protectionFreeze point of the glycol against the 20-year minimum
    Pass
  • Supply in hot, humid hoursHours a year when the rack loop supply rises
    Pass
  • Condensation marginRack loop supply against the dew point of the hall
    Pass
  • Ride-through on power lossSeconds to the rack limit against the fan restart time
    Warning
  • Fluid quality limitsLimits from the rack vendor's sheet
    Warning
  • Part load in each phaseCDU and chiller load against the lowest stable load
    Pass
  • UPS for cooling loadsPumps, fan walls and controls against the UPS size
    Pass
  • Floor loadHighest kN/m² against the slab rating
    Pass
  • Boundary noise at nightdB(A) at the boundary against the local limit
    Pass
  • Weather data licenceOnly weather data with a named, free licence
    Pass
  • Heat pump in each phaseHeat output in each build phase, for the heat customer
    Note

Global2

  • ASHRAE liquid classFacility water supply against the classes W17 to W45
    Pass
  • Air to the racksRack inlet air against the A1 range 18 to 27 °C
    Pass

European Union4

  • Waste heat dutyAbove 1 MW, use the waste heat. EED 2023/1791, Article 26(6)
    Pass
  • F-gas: chiller refrigerantGWP below 750 from 2027. Regulation 2024/573, Annex IV
    Pass
  • KPI reportingApplies at 500 kW or more. Delegated Regulation 2024/1364
    Note
  • Rating forecastA to G scale, adopted, not in force
    Note

Germany2

  • PUE of a new site1.2 or lower. Energy Efficiency Act (EnEfG)
    Pass
  • Reuse share (ERF)10% from July 2026, 15% from 2027, 20% from 2028. EnEfG
    Warning

The rule library

32 rules in 14 rule sets: global, the EU (all 27 countries), Germany, France, the Netherlands, Ireland, the United Kingdom, Singapore, the United States, Japan, China, India, the United Arab Emirates and Australia.

Each rule shows its state, for example "Checked" against the primary source, "Adopted, not in force", "Bill", "Consultation" or "Not transposed". A rule change needs the approval of a reviewer.

Live calculations run for the global, EU and German rules. For the other markets, the app lists each rule and its state. The project limits apply to every site.

The files you issue, and who uses them

All files come from the same model, so the report, the schedule, the drawings and the BIM model show the same numbers.

The report screen of the app: the design report of Hall A beside its export list
FileFormatWhat is in itFor
Design reportPDFSummary and design basis, the liquid loop and heat rejection, heat reuse and carbon, freeze protection, water and noise, redundancy and controls, build phases and structural loads, options and cost over 10 years, the checks, and three appendices: the calculation log, the linked datasheets and the commissioning plan. In English, German, French, Spanish, Dutch or Japanese.Client, authority, reviewer
Equipment scheduleXLSXEach unit with its duty and data. Hall A: 8 CDUs, 15 dry coolers, 3 heat exchangers, 3 chillers, 8 pumps, 7 fan walls, 1 heat pump.Procurement, contractor
Calculation logCSVEvery formula with its inputs and units.Checking engineer
DrawingsPDF, DXF6 sheets: M-001 cooling schematic, M-101 hall layout, M-201 rack loop piping, M-202 facility water piping, M-301 roof plan, M-401 equipment schedule. DXF on your CAD layer standard.CAD team
BIM modelIFC 4.3, IFC4, IFC2x3Racks, CDUs, pipes and plant.BIM coordinator
BMS points listCSV, XLSXThe point count for each unit type, the leak zones with their sensors, and the protocol: BACnet/IP or Modbus TCP.Controls contractor
CFD layoutCSVRack positions, loads and unit data.CFD specialist
Commissioning test sheetsPDFLevels L1 to L5, from the factory tests to the integrated full-load test, with the pass value and the signer of each test.Commissioning agent
Check listCSVEach check with its value, limit, status and source.Reviewer
3D tourMP4The build of the hall, step by step.Client meeting

Why you can trust a value

Real fluid data

CoolProp 8.0.0 gives the density, heat capacity and viscosity at the mean temperature of each loop, not at a fixed 20 °C.

The full year

The energy model runs all 8,760 hours of the PVGIS typical year. The design values come from 25 years of NASA POWER hourly data.

A source on every value

Each value names its source: vendor datasheet, press report, secondary source or sample value. A sample value says so on screen and in the report.

Proven against a reference

For the sample hall, the app gives the same result as an independent reference calculation on all 244 values on its screens.

Full precision inside

The engine keeps SI units at full precision and rounds only on screen, so a rounded number never enters a later step.

Values linked to their proof

Attach a datasheet to the project and link a value to the page that proves it.

Compare designs, and plan for the next GPU

  • Options

    Copies of the design, each run for the full year on the same weather. The table shows PUE, WUE, energy, water, heat reuse and cost, with the best value in each row marked.

  • Make one the design

    This needs your approval, so the design never changes by mistake.

  • Upgrade path

    How far the hall goes with a later GPU generation: 132 kW per rack for GB300 NVL72, and about 190 to 230 kW for Vera Rubin NVL72.

  • Capacity planner

    From MW to GW: the number of racks and the plant for a site size.

Hall AA · Dry coolers and trimB · Warm water, 45 °CC · Chilled water
Hours with no chiller8,612 h8,760 h0 h
Annual PUE1.121.121.33
Cooling energy per year6,062 MWh5,819 MWh26,045 MWh
Heat reuse share (ERF)16.9%24%6%
Equipment, installed5.72 M EUR5.72 M EUR6.30 M EUR

Option B needs racks that take 45 °C coolant.

From draft to an issued revision

  1. 1

    Draft

    Each change saves at once, with undo and redo, also after a restart. Each version shows the changes since the last revision.

  2. 2

    Review

    The reviewer comments on a version. Send the project for review as a file with a passphrase, so only the reviewer can open it.

  3. 3

    Approve

    The reviewer approves with an Ed25519 signature. Any PC can verify the signature.

  4. 4

    Issue

    Only an approved version can be issued. An issued revision is locked, and new work goes into a new draft.

Teams without a server

The owner exports a signed organisation file with the people, the roles and the defaults. Colleagues import it and see the fingerprint of the owner's key.

Your data stays on your PC

  • No server and no account

    The organisation, the projects and the libraries are in a database on your PC.

  • Encrypted on disk

    The database uses SQLCipher with a 256-bit key. The operating system's keychain holds the key.

  • What goes over the network

    The weather download (PVGIS and NASA POWER), the grid carbon data, an update when you agree to it, and the AI provider if you turn it on. No tracking and no crash reports.

  • A record of every change

    Each change goes into a change log with the change and its reverse. A daily backup keeps the last 14 days.

  • An optional AI assistant

    It works on a copy of the design and shows each step. You apply or discard its change. Use a cloud provider, or a local model in Ollama or LM Studio so no project data leaves the PC. Limits for runs, tokens and cost, and an audit log.

  • A Trust page in the app

    It lists each security and governance control with its test and its date. Export it as a PDF for your client.

See it on your own hall

Send us the site and the rack list. In the demo we run your project through all 16 steps and the full year, and you keep the report.

Request a demo
  • Your site's weather year
  • Your rack list and phases
  • The rules of your country
  • Your design report